Meitner 2 Wind
709.1 MW generation in Gray, TX · In queue since June 2025 · Proposed COD June 2028
709.1 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Meitner 2 Wind project is a proposed 709.1 MW wind generation facility in Gray County, Texas. The project, developed by IP Meitner, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0103, with a queue entry date of June 5, 2025. The proposed commercial operation date is June 30, 2028, and the point of interconnection is the 79000 Gray Substation at 345kV.
The project consists of wind turbine technology. It is listed in the ERCOT queue and has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Gray
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Meitner, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
79000 Gray Substation 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Gray Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.