Falls County Storage
60 MW hybrid in Falls, TX · In queue since April 2025 · Proposed COD October 2028
60 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The Falls County Storage project is a proposed 60 MW hybrid battery storage project located in Falls County, Texas. Developed by Aurora Solar LLC, the project consists of battery storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0105, with a queue entry date of April 29, 2025, and a proposed commercial operation date of October 1, 2028.
The point of interconnection for the project is the 3711 BALSW 345kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Aurora Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3711 BALSW 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.