Bendito Wind
300 MW generation in Webb, TX · In queue since July 2025 · Proposed COD July 2029
300 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-13
The Bendito Wind project is a proposed 300 MW wind generation facility in Webb County, Texas. Developed by Bendito Wind Farm, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0117, with a queue entry date of July 29, 2025. The proposed commercial operation date is July 13, 2029.
The point of interconnection for the Bendito Wind project is the Tap 345 kV80220 Cenizo - 80079 Cruce Ckt 2. There has been recent news coverage of the project.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bendito Wind Farm, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV80220 Cenizo - 80079 Cruce Ckt 2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bendito Wind