Apricot Sun Solar
200.84 MW generation in Duval, TX · In queue since April 2025 · Proposed COD September 2029
200.84 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-30
Apricot Sun Solar is a proposed 200.84 MW solar generation project located in Duval County, Texas. The project, under development by Apricot Sun Energy Center, LLC, is interconnected within the ERCOT region under queue ID ERCOT-29INR0124. The project entered the interconnection queue on April 1, 2025, with a proposed commercial operation date of September 30, 2029.
The proposed project consists of photovoltaic solar technology. It is currently listed as active in the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Duval
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Apricot Sun Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 80079 (Cruce) - 5901 (San Miguel) 345 kV Ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.