Caesar Solar
181.6 MW generation in Borden, TX · In queue since July 2025 · Proposed COD November 2029
181.6 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-26
The Caesar Solar project is a proposed 181.6 MW solar generation facility in Borden County, Texas. The project, developed by Caesar Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-29INR0131. It entered the interconnection queue on July 29, 2025, with a proposed commercial operation date of November 26, 2029.
The project is currently listed as active in the ERCOT interconnection queue. The point of interconnection is the 59916 Buck Canyon 345 kV substation. Recent news coverage has discussed the Caesar Solar project.
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Caesar Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59916 Buck Canyon 345 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Caesar Solar