Estrella Dorada Wind
306 MW generation in Duval, TX · In queue since July 2025 · Proposed COD July 2029
306 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-13
The Estrella Dorada Wind project is a proposed 306 MW wind generation facility in Duval County, Texas. The project, developed by Estrella Dorada Wind Farm, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0146, with a queue entry date of July 21, 2025. The proposed commercial operation date is July 13, 2029.
The point of interconnection for the project is Tap 345 kV 80079 Cruce - 5901 San Miguel Ckt 2. The project utilizes wind turbine technology. The Estrella Dorada Wind project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Duval
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Estrella Dorada Wind Farm, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 80079 Cruce - 5901 San Miguel Ckt 2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.