Selenite Springs Solar
300 MW generation in Pecos, TX · In queue since April 2025 · Proposed COD August 2028
300 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
8 months
IA → COD
2y 8m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-08-30
Selenite Springs Solar is a proposed 300 MW solar generation project located in Pecos County, Texas. The project, developed by Selenite Springs Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-29INR0147. The project entered the queue on April 21, 2025, and has a proposed commercial operation date of August 30, 2028.
The project has an Interconnection Agreement (IA) date of December 24, 2025. The point of interconnection (POI) is Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Selenite Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 38355 Leon Creek Switching Station - 38308 Woodhouse Switching Station
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LEONLCPCT1_2
- POI Substation
- Leon Creek Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.