Wolf Bone North Energy Center
1,204 MW generation in Reeves, TX · In queue since October 2025 · Proposed COD November 2029
1,204 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-01
The Wolf Bone North Energy Center is a proposed 1204 MW gas-fired combined-cycle generation project located in Reeves County, Texas. Developed by NRG Wolf Bone Energy Center LLC, the project is listed in the ERCOT interconnection queue as entry ERCOT-29INR0162, with a queue entry date of October 21, 2025. The proposed commercial operation date is November 1, 2029.
The project's point of interconnection (POI) is at the Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 1 and Ckt 2. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NRG Wolf Bone Energy Center LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 1 Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.