LOST PINES GAS RECIP
113.02 MW generation in Bastrop, TX · In queue since July 2025 · Proposed COD August 2029
113.02 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
5 months
IA → COD
3y 8m
Total Duration
5 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2029-08-02
The LOST PINES GAS RECIP project is a proposed 113.02 MW natural gas-fired generation project located in Bastrop County, Texas. The developer is LCRA. The project consists of internal combustion technology.
The project is listed in the ERCOT interconnection queue as entry ERCOT-29INR0166, with a queue entry date of July 7, 2025, and a proposed commercial operation date of August 2, 2029. An Interconnection Agreement (IA) was executed on December 26, 2025. The point of interconnection is the LOST PINES 345 kV substation (#170174). The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
TX
County
Bastrop
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
LCRA
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(#170174) LOST PINES 345 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about LOST PINES GAS RECIP