Tolar Energy Center (ERCOT-29INR0180) — Project Summary

Queue ID
ERCOT-29INR0180
Capacity
1252 MW
Technology
Gas
Status
active
Location
Hood, TX
Region
ERCOT
Developer
NRG Tolar Power LLC
IA Status

Tolar Energy Center

ERCOT-29INR0180BetaActiveGasCombined-CycleERCOTLive · ERCOT

1,252 MW generation in Hood, TX · In queue since September 2025 · Proposed COD November 2029

1,252 MW

Capacity

0

Components

8 months

In Queue

IA Status

COD target: 2029

Interconnection

Total Duration

4y 2m

Pre-Study0%
Queue EntrySep 22, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-11-01

About

The Tolar Energy Center is a proposed 1252 MW gas-fired combined-cycle generation project located in Hood County, Texas. Developed by NRG Tolar Power LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0180, with a queue entry date of September 22, 2025. The proposed commercial operation date is November 1, 2029. The point of interconnection is Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.

The Tolar Energy Center development has been the subject of recent news coverage, with four articles appearing in industry and deals publications.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hood

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NRG Tolar Power LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345 KV circuit 1 from 1440 Comanche Switch to 1900 Comanche Peak SES.

Data Source

Live · ERCOT

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.