Gridline Solar
400 MW generation in Crockett, TX · In queue since August 2025 · Proposed COD July 2029
400 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
Gridline Solar is a proposed 400 MW solar photovoltaic generation project located in Crockett County, Texas. The project, developed by Big Lake Ranch LLC, is in the ERCOT interconnection queue as entry ERCOT-29INR0184, with a queue entry date of August 18, 2025. The proposed commercial operation date is July 1, 2029, at the point of interconnection 76005 Schneeman Draw LCRA.
The Gridline Solar project has been mentioned in recent news coverage related to the electric grid and the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Crockett
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Big Lake Ranch LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76005 Schneeman Draw LCRA
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.