Roan Solar Phase 2
205.9 MW generation in Sterling, TX · In queue since October 2025 · Proposed COD December 2029
205.9 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-15
Roan Solar Phase 2 is a proposed 205.9 MW solar generation project located in Sterling County, Texas. The project, developed by Roan Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0187, with a queue entry date of October 21, 2025. The proposed commercial operation date is December 15, 2029.
The point of interconnection is the Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV line. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Sterling
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Roan Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Divide (#76090) to Sand Bluff Wind Farm (#59902) 345 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Roan Solar Phase 2