Star Of Texas Solar
415 MW generation in Pecos, TX · In queue since August 2025 · Proposed COD July 2029
415 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
The Star Of Texas Solar project is a proposed 415 MW solar generation project in Pecos County, Texas. Developed by BOULEVARD ASSOCIATES, LLC, the project consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0188, with a queue entry date of August 18, 2025, and a proposed commercial operation date of July 1, 2029.
The point of interconnection (POI) for the project is Tap AEP Solstice (60404) to Bakersfield (76002) 345kV. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BOULEVARD ASSOCIATES, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap AEP Solstice (60404) to Bakersfield (76002) 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.