Glass Mountain Wind 1
511.5 MW generation in Reeves, TX · In queue since January 2026 · Proposed COD December 2028
511.5 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Glass Mountain Wind 1 is a proposed 511.5 MW wind generation project located in Reeves County, Texas. The project, developed by Glass Mountain Wind, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0194, with a queue entry date of January 13, 2026. The proposed commercial operation date is December 31, 2028.
The point of interconnection is Tap 345 60404 SOLSTICE - 18669 TOYAHCRK_5. This development project has been the subject of recent news coverage, with 10 articles categorized under the industry sector.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Glass Mountain Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 60404 SOLSTICE - 18669 TOYAHCRK_5
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.