Spurland Solar II
201.6 MW generation in Dickens, TX · In queue since November 2025 · Proposed COD December 2028
201.6 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-30
The Spurland Solar II project is a proposed 201.6 MW solar generation facility in Dickens County, Texas. The project, developed by Spurland Solar II, is located within the ERCOT region and consists of photovoltaic solar technology. It is listed in the ERCOT interconnection queue as entry ERCOT-29INR0195, with a queue entry date of November 5, 2025, and a proposed commercial operation date of December 30, 2028.
The project's point of interconnection (POI) is the 59908 Nova Prime 345 345kV substation. As of the latest data, the project has an active status in the interconnection queue. The project has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Spurland Solar II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59908 Nova Prime 345 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Spurland Solar II