Miller Bend Energy BESS
547.62 MW hybrid in Young, TX · In queue since December 2025 · Proposed COD June 2029
547.62 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
Miller Bend Energy BESS is a proposed hybrid energy project located in Young County, Texas, with a total capacity of 547.62 MW. The project, developed by Miller Bend Energy, consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0204, with a queue entry date of December 17, 2025, and a proposed commercial operation date of June 1, 2029.
The point of interconnection (POI) for the project is the Tap 345kV (Bus1#1430) Graham SES to (Bus2#11050) Dusty Road.
Generated from interconnection queue and public data sources
State
TX
County
Young
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Miller Bend Energy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV (Bus1#1430) Graham SES to (Bus2#11050) Dusty Road
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.