Sawtooth Solar
201.36 MW generation in Runnels, TX · In queue since November 2025 · Proposed COD August 2030
201.36 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-08-01
Sawtooth Solar is a proposed 201.36 MW solar photovoltaic generation project in Runnels County, Texas. Developed by Sawtooth Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0210, with a queue entry date of November 24, 2025. The proposed commercial operation date is August 1, 2030.
The point of interconnection for Sawtooth Solar is planned at a tap to the 345kV Odysseus (Bus#60072) to Bluff Creek (Bus #60040) line. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Runnels
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sawtooth Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap to the 345kV Odysseus (Bus#60072) to Bluff Creek (Bus #60040) line
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.