Paint Brush PV4
251.5 MW generation in Coleman, TX · In queue since December 2025 · Proposed COD December 2029
251.5 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The Paint Brush PV4 project is a proposed 251.5 MW solar generation facility in Coleman County, Texas. Developed by Renew Development HoldCo LLC, the project consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0221, with a queue entry date of December 2, 2025. The proposed commercial operation date is December 31, 2029.
The point of interconnection for Paint Brush PV4 is the Tap 345 1444 Brown Switch – 60040 Bluff Creek Switch. The project is listed as active in the interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Coleman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Renew Development HoldCo LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 1444 Brown Switch – 60040 Bluff Creek Switch
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.