Velveteen Solar II
300.9 MW generation in Baylor, TX · In queue since December 2025 · Proposed COD December 2029
300.9 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-15
The Velveteen Solar II project is a proposed 300.9 MW solar generation facility in Baylor County, Texas. The project, under development by Velveteen Solar II, LLC, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0225, with a queue entry date of December 23, 2025, and a proposed commercial operation date of December 15, 2029.
The point of interconnection (POI) for the project is planned as a tap into the 6076 FOXTAIL- 6100 OKLAUNION line.
Generated from interconnection queue and public data sources
State
TX
County
Baylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Velveteen Solar II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap into 6076 FOXTAIL- 6100 OKLAUNION
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Velveteen Solar II