Brazos Energy Center 1 (ERCOT-29INR0229) — Project Summary

Queue ID
ERCOT-29INR0229
Capacity
300.76 MW
Technology
Battery
Status
active
Location
McLennan, TX
Region
ERCOT
Developer
Ferrovial Energy US 1
IA Status

Brazos Energy Center 1

ERCOT-29INR0229BetaActiveOtherBattery Energy StorageERCOTLive · ERCOT

300.76 MW hybrid in McLennan, TX · In queue since January 2026 · Proposed COD September 2029

300.76 MW

Capacity

0

Components

4 months

In Queue

IA Status

COD target: 2029

Interconnection

Total Duration

3y 8m

Pre-Study0%
Queue EntryJan 13, 2026

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-18

About

The Brazos Energy Center 1 is a proposed 300.76 MW hybrid energy project located in McLennan County, Texas. Developed by Ferrovial Energy US 1, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0229, with a queue entry date of January 13, 2026, and a proposed commercial operation date of September 18, 2029.

The project is listed as a hybrid project in the ERCOT queue. Recent news coverage indicates industry interest in the development.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

McLennan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Ferrovial Energy US 1

Utility

Entity

ERCOT

Service Type

Point of Interconnection

POSSUMTROT_5

Data Source

Live · ERCOT

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.