Enfinity Redbud Storage
516.05 MW hybrid in Comal, TX · In queue since February 2026 · Proposed COD December 2029
516.05 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-18
The Enfinity Redbud Storage project is a proposed 516.05 MW hybrid development in Comal County, Texas. The project, being developed by EG Redbud LLC, consists of battery energy storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0242, with a queue entry date of February 10, 2026, and a proposed commercial operation date of December 18, 2029.
The point of interconnection for the project is the 345kV Hays Energy (7043) to 345kV Bergheim (7770) line.
Generated from interconnection queue and public data sources
State
TX
County
Comal
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EG Redbud LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV Hays Energy (7043) - 345kV Bergheim (7770)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW