Sugarberry Solar
127.3 MW generation in Kinney, TX · In queue since February 2026 · Proposed COD December 2029
127.3 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-18
Sugarberry Solar is a proposed 127.3 MW solar generation project located in Kinney County, Texas. The project, developed by EG Sugarberry LLC, is listed in the ERCOT interconnection queue as entry ERCOT-29INR0251, with a queue entry date of February 13, 2026. The proposed commercial operation date is December 18, 2029.
The project utilizes photovoltaic solar technology. It is currently listed as active in the interconnection queue. The point of interconnection is the 78255 Pinto Creek 138 kV location.
Generated from interconnection queue and public data sources
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EG Sugarberry LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
78255 Pinto Creek 138 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ZIER_SLR_ALL
- POI Substation
- Pinto Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.