Los Toros Energy Center Solar SLF
401.4 MW generation in Dawson, TX · In queue since February 2026 · Proposed COD September 2029
401.4 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
The Los Toros Energy Center Solar SLF project is a proposed 401.4 MW solar generation facility in Dawson County, Texas. The project, being developed by Los Toros Energy Center, LLC, is interconnected within the ERCOT region under queue ID ERCOT-29INR0255. It entered the interconnection queue on February 25, 2026, with a proposed commercial operation date of September 1, 2029.
The project is currently listed as active in the ERCOT interconnection queue. It utilizes photovoltaic solar technology. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Dawson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Los Toros Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1169 ALKALI_LAKE 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.