Los Toros Energy Center Storage SLF
— hybrid in Dawson, TX · In queue since February 2026 · Proposed COD September 2029
—
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
The Los Toros Energy Center Storage SLF project is a proposed hybrid development project located in Dawson County, Texas. The project, developed by Los Toros Energy Center, LLC, consists of battery energy storage and another unspecified technology. It has a total capacity of 0 MW.
The project is listed in the ERCOT interconnection queue as entry ERCOT-29INR0271, with a queue entry date of February 26, 2026. The proposed commercial operation date is September 1, 2029. The project's interconnection status is currently active.
Generated from interconnection queue and public data sources
State
TX
County
Dawson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Los Toros Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1169 ALKALI_LAKE 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.