Tierra Loma Storage
200 MW hybrid in Crane, TX · In queue since February 2026 · Proposed COD September 2029
200 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
The Tierra Loma Storage project is a proposed 200 MW hybrid battery energy storage project located in Crane County, Texas. Developed by Tierra Loma Solar, LLC, the project entered the ERCOT interconnection queue on February 19, 2026, under queue ID ERCOT-29INR0280. The proposed commercial operation date is September 1, 2029.
The project is a hybrid facility consisting of battery energy storage paired with another unspecified technology. It is currently listed as active in the ERCOT interconnection queue. The point of interconnection is Tap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1.
Generated from interconnection queue and public data sources
State
TX
County
Crane
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tierra Loma Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV #18668 ROCK DRAW - #76000 NORTH MCCAMEY ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.