Flurry Gas 1
112 MW generation in Midland, TX · In queue since February 2026 · Proposed COD January 2029
112 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2029
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-31
Flurry Gas 1 is a proposed 112 MW gas-fired combined-cycle generation project located in Midland County, Texas. The developer is NET Power Canaveral LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-29INR0305, with a queue entry date of February 25, 2026, and a proposed commercial operation date of January 31, 2029.
The project is currently listed as active in the interconnection queue. Flurry Gas 1 has been the subject of recent news coverage, with 10 articles categorized as industry, regulatory, and grid-related.
Generated from interconnection queue and public data sources
State
TX
County
Midland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NET Power Canaveral LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1185 Midland County Northwest Switch (bus #1185) – Midland East (bus #1021) 345 kV Line Ckt 01
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Midland County Northwest Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.