Solgen Storage
150.3 MW hybrid in Lampasas, TX · In queue since April 2025 · Proposed COD August 2029
150.3 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-08-30
The Solgen Storage project is a proposed 150.3 MW hybrid development in Lampasas County, Texas. The project, sponsored by Lampasas Hybrid Energy LLC, consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-30INR0038.
The project entered the queue on April 25, 2025, with a proposed commercial operation date of August 30, 2029. The point of interconnection is the 7066 Adamsville 138kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Lampasas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lampasas Hybrid Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7066 Adamsville 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Adamsville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Solgen Storage