Bell Song Solar
167.6 MW generation in Jim Hogg, TX · In queue since June 2025 · Proposed COD September 2029
167.6 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-15
Bell Song Solar is a proposed 167.6 MW solar generation project located in Jim Hogg County, Texas. The project, developed by Bell Song Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-30INR0041, with a queue entry date of June 12, 2025. The proposed commercial operation date is September 15, 2029.
The project utilizes photovoltaic solar technology. It is currently listed as "active" in the interconnection queue. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Jim Hogg
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bell Song Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV #80079 CRUCE7A - #80355 DELSOL7A ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bell Song Solar