La Morena Energy Center Solar
250 MW generation in Zapata, TX · In queue since June 2025 · Proposed COD May 2029
250 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-07
The La Morena Energy Center Solar project is a proposed 250 MW solar generation project located in Zapata County, Texas. Developed by Adapture Solar Development, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue as ERCOT-30INR0043 on June 12, 2025. The proposed commercial operation date is May 7, 2029.
The project is currently listed as active in the interconnection queue. The point of interconnection is Tap 345 kV (80225) CENIZO7C - (80307) DELSOL7C.
Generated from interconnection queue and public data sources
State
TX
County
Zapata
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Adapture Solar Development
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV (80225) CENIZO7C - (80307) DELSOL7C
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.