Bell Song Solar 2
167.6 MW generation in Jim Hogg, TX · In queue since June 2025 · Proposed COD March 2030
167.6 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2030
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-16
Bell Song Solar 2 is a proposed solar generation project located in Jim Hogg County, Texas, with a total capacity of 167.6 MW. The project, being developed by Bell Song Solar, LLC 2, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-30INR0049, with a queue entry date of June 12, 2025, and a proposed commercial operation date of March 16, 2030.
The point of interconnection is Tap 345kV (#80079) CRUCE7A - (#80355) DELSOL7A ckt 1. The development has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Jim Hogg
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bell Song Solar, LLC 2
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV (#80079) CRUCE7A - (#80355) DELSOL7A ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.