Springfield Solar
400 MW generation in Pecos, TX · In queue since September 2025 · Proposed COD August 2028
400 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
3 months
IA → COD
2y 8m
Total Duration
3 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-08-30
Springfield Solar is a proposed 400 MW solar generation project located in Pecos County, Texas. Developed by BOULEVARD ASSOCIATES, LLC, the project consists of photovoltaic solar technology and is interconnected within the ERCOT region. It is listed in the ERCOT interconnection queue as entry ERCOT-30INR0058, with a queue entry date of September 9, 2025, and a proposed commercial operation date of August 30, 2028. The project's Interconnection Agreement (IA) date is December 24, 2025.
The Point of Interconnection (POI) is the Tap Leon Creek (#38355) to Woodhouse Station (#38308) 138kV line. The Springfield Solar project has been mentioned in recent news coverage, with 11 articles categorized as industry, grid, and regulatory.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BOULEVARD ASSOCIATES, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Leon Creek (#38355) to Woodhouse Station (#38308) 138kV line
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26