Prairie Ridge (Gas - CC)
1,660.4 MW generation in Franklin, TX · In queue since December 2025 · Proposed COD June 2032
1,660.4 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2032
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-06-01
The Prairie Ridge (Gas - CC) project is a proposed 1660.4 MW natural gas combined-cycle generation project located in Franklin County, Texas. The project is being developed by Tenaska Power Generation, LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-30INR0071, with a queue entry date of December 1, 2025. The proposed commercial operation date is June 1, 2032.
The point of interconnection (POI) for the project is the TAP 345 KV line between substations 11699 WOODARD and 11702 BEARPEN. The project currently has an active status within the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tenaska Power Generation, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV 11699 WOODARD - 11702 BEARPEN
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Woodward
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.