Moon Hammer
1,300 MW generation in Wheeler, TX · In queue since January 2026 · Proposed COD November 2030
1,300 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
Signed Dec 2025
IA → COD
4y 11m
Total Duration
4 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2030-11-30
Moon Hammer is a proposed 1300 MW gas-fired generation project located in Wheeler County, Texas. The project, developed by Moon Hammer LLC, is in the ERCOT interconnection queue as entry ERCOT-30INR0077, with a queue entry date of January 13, 2026. The proposed commercial operation date is November 30, 2030. An Interconnection Agreement (IA) was executed on December 19, 2025. The point of interconnection (POI) is a tap on the 345 kV line between Tesla and Grey.
The Moon Hammer project has been the subject of recent news coverage, appearing in 49 news articles, primarily related to deals and grid infrastructure.
Generated from interconnection queue and public data sources
State
TX
County
Wheeler
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Moon Hammer LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV line between Tesla & Grey
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.