Permian I Wind
636.52 MW generation in Pecos, TX · In queue since January 2026 · Proposed COD June 2030
636.52 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2030
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-30
Permian I Wind is a proposed wind generation project located in Pecos County, Texas, within the ERCOT region. The project, developed by S&S Renewables, LLC, has a total capacity of 636.52 MW. It is listed in the ERCOT interconnection queue as entry ERCOT-30INR0086, with a queue entry date of January 26, 2026, and a proposed commercial operation date of June 30, 2030. The point of interconnection is the Tap TNMP White Baker (38435)–Bottlebrush (38441) 345-kV double-circuit.
The Permian I Wind project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
S&S Renewables, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26