Mistflower Energy Center Storage
312.85 MW hybrid in Runnels, TX · In queue since February 2026 · Proposed COD June 2030
312.85 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2030
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The Mistflower Energy Center Storage project is a proposed 312.85 MW hybrid development in Runnels County, Texas. The project, developed by Mistflower Energy Center LLC, consists of battery storage and other unspecified technologies. It is located within the ERCOT region and has interconnection queue ID ERCOT-30INR0089.
The project entered the ERCOT interconnection queue on February 25, 2026, with a proposed commercial operation date of June 1, 2030. The point of interconnection is Tap 345kV 60072 Odysseus – 60040 Bluff Creek. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
TX
County
Runnels
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mistflower Energy Center LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60072 Odysseus – 60040 Bluff Creek
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.