FPL-107
1,300 MW generation in Miami-Dade, FL · In queue since August 2007 · Proposed COD June 2027
1,300 MW
Capacity
1
Components
Nuclear
18y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
19y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The proposed FPL-107 project is a 1300 MW nuclear generation facility in Miami-Dade County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Turkey Point Substation. It is currently in the Florida Power & Light interconnection queue with an entry date of August 30, 2007. The proposed commercial operation date is June 1, 2027, and the project's interconnection status is currently in the Facility Study phase.
The FPL-107 project has been the subject of recent news coverage, with 11 articles categorized as industry-related and regulatory matters.
Generated from interconnection queue and public data sources
State
FL
County
Miami-Dade
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Turkey Point Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14