FPL-108
1,300 MW generation in Miami-Dade, FL · In queue since August 2007 · Proposed COD June 2028
1,300 MW
Capacity
1
Components
Nuclear
18y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
20y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
FPL-108 is a proposed 1300 MW nuclear generation project located in Miami-Dade County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Power & Light system. It entered the interconnection queue on August 30, 2007, and has a proposed commercial operation date of June 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of a single 1300 MW nuclear component. The point of interconnection is the Turkey Point Substation.
Generated from interconnection queue and public data sources
State
FL
County
Miami-Dade
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Turkey Point Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-108