FPL-191
74.5 MW generation in Manatee, FL · In queue since May 2016 · Proposed COD December 2026
74.5 MW
Capacity
1
Components
Solar
10 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The proposed project FPL-191 is a 74.5 MW solar generation project located in Manatee County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Florida Power & Light system at the Keentown-Manatee 230kV point of interconnection.
The project is currently active in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of May 9, 2016. The proposed commercial operation date is December 31, 2026. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Manatee
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Keentown-Manatee 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.