FPL-263
74.5 MW generation in Palm Beach, FL · In queue since June 2017 · Proposed COD January 2025
74.5 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
7y 7m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-31
FPL-263 is a proposed solar generation project with a total capacity of 74.5 MW, located in Palm Beach County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Power & Light system at the Cedar-Corbett 230kV point of interconnection.
The project is currently in the Facility Study phase within the Florida Reliability Coordinating Council (FRCC) interconnection queue, having entered the queue on June 27, 2017. The proposed commercial operation date (COD) is January 31, 2025.
Generated from interconnection queue and public data sources
State
FL
County
Palm Beach
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Cedar-Corbett 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-263