FPL-265
74.5 MW generation in Putnam, FL · In queue since June 2017 · Proposed COD November 2024
74.5 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
7y 5m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-11-15
FPL-265 is a proposed solar generation project located in Putnam County, Florida, with a total capacity of 74.5 MW. The project, developed by a third party, is interconnected with Florida Power & Light (FPL) and is in the FPL interconnection queue as of June 27, 2017. The proposed commercial operation date is November 15, 2024, and the Interconnection Agreement (IA) has been executed.
The project consists of 74.5 MW of solar photovoltaic generation. The point of interconnection is the Korona-Putnam 230kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Putnam
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Korona-Putnam 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.