FPL-280
74.5 MW generation in Hendry, FL · In queue since June 2017 · Proposed COD January 2027
74.5 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-31
FPL-280 is a proposed solar generation project located in Hendry County, Florida, with a total capacity of 74.5 MW. The developer is Florida Power & Light (FPL). This project is in the Florida Power & Light interconnection queue, with an entry date of June 27, 2017. The proposed commercial operation date is January 31, 2027. The interconnection status is currently in the Facility Study phase.
The point of interconnection for FPL-280 is the Andytown-Orange River 500kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Andytown-Orange River 500kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-280