FPL-293
74.5 MW generation in Nassau, FL · In queue since June 2017 · Proposed COD January 2025
74.5 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
7y 7m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-31
FPL-293 is a proposed solar generation project with a total capacity of 74.5 MW. Located in Nassau County, Florida, the project is being developed by Florida Power & Light (FPL). It consists of 74.5 MW of solar photovoltaic generation.
The project is currently active in the Florida Power & Light interconnection queue, with an entry date of June 27, 2017. The proposed commercial operation date is January 31, 2025. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Duval-Yulee 230kV line.
Generated from interconnection queue and public data sources
State
FL
County
Nassau
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Duval-Yulee 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-293