FPL-354
74.5 MW hybrid in Putnam, FL · In queue since July 2018 · Proposed COD December 2023
74.5 MW
Capacity
1
Components
Solar
7y 10m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
5y 5m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-12-30
The proposed project FPL-354 is a 74.5 MW solar and battery hybrid development located in Putnam County, Florida. The project, being developed by a Third Party developer, interconnected to Florida Power & Light (FPL). It consists of 74.5 MW of solar capacity.
The project is in the FPL interconnection queue with an entry date of July 30, 2018. The proposed commercial operation date is December 30, 2023, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Putnam
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Rice Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-354