FPL-356
74.5 MW generation in Brevard, FL · In queue since July 2018 · Proposed COD January 2025
74.5 MW
Capacity
1
Components
Solar
7y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
6y 6m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-31
FPL-356 is a proposed solar generation project located in Brevard County, Florida, with a total capacity of 74.5 MW. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Power & Light system at the Heritage Solar-Malabar 230kV point of interconnection.
The project is listed in the Florida Reliability Coordinating Council (FRCC) interconnection queue with an entry date of July 30, 2018. The proposed commercial operation date is January 31, 2025, and the project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Brevard
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Heritage Solar-Malabar 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.