74.5 MW generation in Brevard, FL · In queue since July 2018 · Proposed COD July 2028
74.5 MW
Capacity
1
Components
Solar
7y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
10 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
FPL-357 is a proposed solar generation project with a total capacity of 74.5 MW, located in Brevard County, Florida. The developer and interconnecting utility for the project is Florida Power & Light (FPL). The project is in the Florida Power & Light interconnection queue with an entry date of July 30, 2018.
The proposed commercial operation date for FPL-357 is July 31, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the Heritage Solar-Malabar 230kV substation.
Generated from interconnection queue and public data sources
State
FL
County
Brevard
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Heritage Solar-Malabar 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.