FPL-366A
74.5 MW generation in Calhoun, FL · In queue since February 2019 · Proposed COD January 2025
74.5 MW
Capacity
1
Components
Solar
7y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
5y 11m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-31
FPL-366A is a proposed solar generation project with a total capacity of 74.5 MW, located in Calhoun County, Florida. The developer is Florida Power & Light (FPL). It is currently an active project in the Florida Power & Light interconnection queue, with an entry date of February 21, 2019. The proposed commercial operation date is January 31, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Smith- Sinai Cemetery 230kV line.
Generated from interconnection queue and public data sources
State
FL
County
Calhoun
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Smith- Sinai Cemetery 230kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-366A