FPL-366D
74.9 MW generation in Okaloosa, FL · In queue since April 2019 · Proposed COD October 2027
74.9 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-15
The proposed project FPL-366D is a 74.9 MW solar generation project located in Okaloosa County, Florida. The developer is listed as Third Party, and the interconnecting utility is Florida Power & Light (FPL). This project is actively listed in the FPL interconnection queue with an entry date of April 18, 2019, and a proposed commercial operation date of October 15, 2027. The point of interconnection is the Shoal River - Samson (APC) 230 kV line.
The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Okaloosa
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Shoal River - Samson (APC) 230 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-366D