FPL-370
74.9 MW generation in Putnam, FL · In queue since September 2019 · Proposed COD December 2024
74.9 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
5y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-12-04
The proposed project FPL-370 is a 74.9 MW solar generation project located in Putnam County, Florida. The developer is listed as a Third Party, and the interconnecting utility is Florida Power & Light (FPL). The project entered the FPL interconnection queue on September 13, 2019, and has a proposed commercial operation date of December 4, 2024. The interconnection agreement (IA) has been executed.
The point of interconnection (POI) is the Springbank-Seminole Plant (SEC) 230kV.
Generated from interconnection queue and public data sources
State
FL
County
Putnam
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Springbank-Seminole Plant (SEC) 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-370