Project FPL-378H — Project Summary

Queue ID
FPL-378H
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Walton, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

FPL-378H

FPL-378HBetaActiveSolarFPLLBNL

74.5 MW generation in Walton, FL · In queue since February 2020 · Proposed COD July 2027

74.5 MW

Capacity

1

Components

Solar

6y 3m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

7y 5m

Facilities Study50%
Queue EntryFeb 5, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-31

About

The proposed FPL-378H project is a 74.5 MW solar generation project located in Walton County, Florida. The project, being developed by Florida Power & Light (FPL), entered the queue on February 5, 2020, and has a proposed commercial operation date of July 31, 2027.

The project is currently in the Facility Study phase of its interconnection process with Florida Power & Light. The point of interconnection is the Shoal River - Pinckard (APC) 230kV line.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Walton

Grid Region

Southeast

Market

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Service Type

Point of Interconnection

Shoal River - Pinckard (APC) 230kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project FPL-378H