FPL-380D
20 MW generation in Calhoun, FL · In queue since February 2020 · Proposed COD October 2027
20 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-15
The proposed project FPL-380D is a 20 MW solar generation project located in Calhoun County, Florida. The developer is listed as a Third Party, and the interconnecting utility is Florida Power & Light (FPL). It is in the FPL interconnection queue with an entry date of February 27, 2020, and a proposed commercial operation date of October 15, 2027. The project's point of interconnection is the Altha - Gaskin (PS) 115kV line.
The project has an Interconnection Agreement (IA) that has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Calhoun
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Altha - Gaskin (PS) 115kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-380D